The first of two dormitory sections of the LNG Canada camp at Kitimat is now being assembled. (Photo courtesy LNG Canada) One of the more visible above-ground projects now underway is that of the worker camp, Cedar Valley Lodge. (Contributed photo)

Workers’ camp at LNG facility in Kitimat takes shape

Extensive worker camp now being assembled

Born in Ireland but having spent years overseeing liquefied natural gas (LNG) construction projects in Australia, LNG Canada’s just-arrived general manager for its $40 billion facility in Kitimat is firm about his expectations.

“We want this to be the safest project on earth,” Vince Kenny says of construction which has just passed the one year mark leading to a planned finish in 2024.

With just under 1,000 people now working at the 400-hectare site, now is the time to cement that standard, he says.

“By the time we get to 5,000 people, we will have that culture in place,” Kenny emphasizes that this project which will be his seventh. “Unless we’ve got a culture, all the systems, processes and procedures are ineffective.”

Employees begin each shift reviewing the work plan, a procedure called a toolbox discussion.

“We’re here to take care of one another,” says Kenny, translating the IIF acronym that’s the hallmark of LNG Canada — Incident and Injury Free.

Even a brief tour of the works by a group of journalists from across B.C. starts with a video of LNG Canada workers outlining safety and security, the two words being almost interchangeable.

Workers have ID cards to be ‘badged in,’ creating an electronic record of their presence. They’re required to stay within their designated work area. There are constant security patrols. Vehicles are inspected for any fluid leaks before entry. There’s specific mention of drug-sniffing dogs too.

READ MORE: Okanagan company wins contract for LNG Canada project in Kitimat

No one gets on the site without basic safety equipment — hardhat, safety glasses, a high visibility vest, work boots and gloves. The driver of the tour bus taking the journalists to the site points out emergency exit windows. He brandishes a small hammer to smash a window if necessary. The bus doesn’t move until each passenger clicks in their seatbelt.

Victor Kenny, LNG Canada general manager

With Kenny is Trevor Feduniak who arrived in Kitimat in mid-2016. As the project site manager, he was one of the first senior LNG Canada people on location, overseeing the clearing of the former Methanex site and then expanding its footprint.

Although the project was not given the formal go-ahead until last October by LNG Canada’s investors Shell, PETRONAS from Malaysia, PetroChina from China, Mitsubishi Corporation from Japan and Korean-owned KOGAS, crews had been fully occupied raising up the location to a construction standard and to safeguard it against the possibility of tsunami sweeping inland from the Douglas Channel.

The fill comes from the nearby Sandhill, a mountain of material Feduniak describes as perfect for its material composition. One million cubic metres has already been transferred, edging away at the overall 2.5 million cubic metres that will have to be moved and placed in preparation for the arrival of two massive processing modules. From there, the gas will be transported via a pipeline from northeastern B.C., super-cooled to a liquid state for storage and then shipped out on specialized tankers to Asian customers.

“This is what we call coming out of the ground,” Feduniak explains as a tour bus winds its way through the site, encountering massive material-carrying trucks along the way.

Two streams that cross the site, the Kitimat Side Channel and Beaver Creek, were diverted to ensure Fluor-JGC has dry and stable conditions on which to construct the plant.

“When you disturb one habitat, you have to compensate with two [enhancement measures],” says Feduniak of the environmental work that was involved.

He compares the detailed water course replacement work for fish and other habitat to that of a landscaped Japanese garden.

One corner of the project site contains what, to the untrained eye, looks like sections of pipe stacked metres above the ground.

What they are are the pilings, 40 metres long, that will be driven into the ground upon which the two processing buildings will sit.

READ MORE: LNG Canada cost to exceed stated $40 billion price tag

Those processing modules being built in Asia are to be 70 metres long, 35 metres wide and 50 metres tall, the approximate height of a 13-storey commercial building.

They’ll be shipped to Kitimat in modular segments and assembled on-site, being transported to their final resting place via an elaborate series of interconnected trailers with hundreds of wheels controlled by a single operator using a remote control. So sophisticated is the transport system that the operator is able to place the modules within centimetres of where they need to be located.

The sheer height of the modules has meant raising Rio Tinto BC Works’ power lines that cross the site to deliver power to the smelter from Kemano, so that the modules can fit comfortably underneath when being moved.

One of the more visible above-ground projects now underway is that of the worker camp, Cedar Valley Lodge, which is being built by the ATCO-Bird joint venture, for another joint venture between Fluor Corporation and JGC, the overall general contractor on the project.

There’ll be two living unit sections with a series of common buildings in the middle.

One of the modular accommodation sections is now being assembled with a finishing schedule of next spring to meet a first goal of 1,500 “heads in beds” with 1,000 more beds to be added each quarter thereafter to the final total of 4,500.

Unlike camps of past, each worker will have his or her own bathroom and each room will have its own TV. There’ll be sound dampening and other acoustic methods so that sleeping quarters will be as quiet as possible. The living areas will be co-ed.

The middle buildings will contain administration offices, sports and recreation facilities including male and female gyms, kitchen and dining facilities, an entertainment centre, a licensed lounge, a medical clinic, storage for luggage and housekeeping and maintenance facilities.

There’ll be landscaping around the area and informational material describes the facility as having the “largest core footprint” of its kind in Canada.

“You want your workers to come here and then want to come back,” said LNG Canada spokesperson Susannah Pierce of the atmosphere and amenities of the facility.

More than 4,500 people will be onsite at any one time at the peak of construction, requiring between 7,000 to 7,500 people in all given the shift work nature of the project. Workers will be onsite for 14 days at a time, returning after a seven-day break.

All this compares to another large worker camp in B.C. — the 1,600-room facility at B.C. Hydro’s Site C project in northeastern B.C.

With accommodation facilities now underway, there’s other activity on the waterfront at two terminal sites.

LNG Canada is building Rio Tinto a new wharf in exchange for taking over the aluminum smelting company’s existing wharf. Dredging is now going on as part of that project.

kitimatLNGlng canada

Get local stories you won't find anywhere else right to your inbox.
Sign up here

 

LNG Canada project site manager Trevor Feduniak arrived in Kitimat in mid-2016. (Natalia Balcerzak/Terrace Standard)

LNG Canada’s ‘fish ladder’ at Anderson Creek, which allows fish to migrate despite construction-related work. (Natalia Balcerzak/Terrace Standard)

The middle buildings will contain administration offices, sports and recreation facilities including male and female gyms, kitchen and dining facilities, and other features. (Natalia Balcerzak/Terrace Standard)

Just Posted

NDP headquarters on election night, Oct. 24, 2020. (Katya Slepian/Black Press Media)
ELECTION 2020: Live blog from B.C. party headquarters

BC NDP projected to win majority government – but celebrations will look different this election

North Coast BC NDP MLA Incumbent is seen with her wife Andrea Wilmot and their son Lua, as well as their dog Duncan. Preliminary results on election night Oct. 24 show Rice is in for a third term. (Photo: K-J Millar/The Northern View)
Jennifer Rice is North Coast MLA for third term

Preliminary election results show NDP Majority government

B.C. Green Party leader Sonia Furstenau outlines her party's climate action platform at Nanaimo's Vancouver Island Conference Centre earlier this month. (News Bulletin file photo)
Green leader Furstenau declared victor in her home riding on Vancouver Island

Cowichan Valley voters elect freshly minted party leader for her second term

John Horgan has been re-elected the MLA for Langford-Juan de Fuca. (File-Black Press)
Horgan trounces challengers to be re-elected in his Vancouver Island riding

MLA has represented constituency of Langford-Juan de Fuca and its predecessors since 2005

Poppy donation boxes have been delivered to restaurants, cafes, stores and places of businesses in Prince Rupert by the Royal Canadian Legion Branch 127 for the 2020 National Poppy Campaign. (Photo: K-J Millar/The Northern View)
National poppy campaign restricted by COVID-19

Prince Rupert Royal Canadian legion expects less donations to offer vital assistance to local vets

NDP Leader John Horgan celebrates his election win in the British Columbia provincial election in downtown Vancouver, B.C., Saturday, Oct. 24, 2020. THE CANADIAN PRESS/Jonathan Hayward
Horgan celebrates projected majority NDP government, but no deadline for $1,000 deposit

Premier-elect says majority government will allow him to tackle issues across all of B.C.

FILE – Prime Minister Justin Trudeau greets Premier John Horgan during a press conference at the BC Transit corporate office following an announcement about new investments to improve transit for citizens in the province while in Victoria on Thursday, July 18, 2019. THE CANADIAN PRESS/Chad Hipolito
Trudeau congratulates Horgan on NDP’s election victory in British Columbia

Final count won’t be available for three weeks due to the record number of 525,000 ballots cast by mail

Comedic actor Seth Rogen, right, and business partner Evan Goldberg pose in this undated handout photo. When actor Seth Rogen was growing up and smoking cannabis in Vancouver, he recalls there was a constant cloud of shame around the substance that still lingers. Rogen is determined to change that. (Maarten de Boer ohoto)
Seth Rogen talks about fighting cannabis stigma, why pot should be as accepted as beer

‘I smoke weed all day and every day and have for 20 years’

Provincial Green Party leader Sonia Furstenau speaks at Provincial Green Party headquarters at the Delta Victoria Ocean Pointe in Victoria. (Arnold Lim / Black Press)
VIDEO: Furstenau leads BC Greens to win first riding outside of Vancouver Island

Sonia Furstenau became leader of BC Greens one week before snap election was called

NDP Leader John Horgan elbow bumps NDP candidate Coquitlam-Burke Mountain candidate Fin Donnelly following a seniors round table in Coquitlam, B.C., Tuesday, October 20, 2020. THE CANADIAN PRESS/Jonathan Hayward
Horgan, NDP head for majority in B.C. election results

Record number of mail-in ballots may shift results

Join Black Press Media and Do Some Good

Pay it Forward program supports local businesses in their community giving

The Canadian border is pictured at the Peace Arch Canada/USA border crossing in Surrey, B.C. Friday, March 20, 2020. More than 4.6 million people have arrived in Canada since the border closed last March and fewer than one-quarter of them were ordered to quarantine while the rest were deemed “essential” and exempted from quarantining. THE CANADIAN PRESS/Jonathan Hayward
Majority of international travellers since March deemed ‘essential’, avoid quarantine

As of Oct. 20, 3.5 million travellers had been deemed essential, and another 1.1 million were considered non-essential

Canada’s Chief Public Health Officer Theresa Tam responds to a question during a news conference Friday October 23, 2020 in Ottawa. Canada’s top physician says she fears the number of COVID-19 hospitalizations and deaths may increase in the coming weeks as the second wave continues to drive the death toll toward 10,000. THE CANADIAN PRESS/Adrian Wyld
Canada’s top doctor warns severe illness likely to rise, trailing spike in COVID-19 cases

Average daily deaths from virus reached 23 over the past seven days, up from six deaths six weeks ago

Most Read