Pacific Northern Gas wants to add compressor stations, such as this one at Telkwa, to increase the flow of natural gas through its line serving northwestern B.C. (Photo courtesy Pacific Northern Gas.)

Pacific Northern Gas wants to add compressor stations, such as this one at Telkwa, to increase the flow of natural gas through its line serving northwestern B.C. (Photo courtesy Pacific Northern Gas.)

LNG projects hold out potential for lower gas user rates

LNG plants planned for Port Edward and Terrace

Pacific Northern Gas is offering up the prospect of lower rates for its existing customers in the northwest provided two small-scale natural gas liquefaction projects go ahead.

Port Edward LNG on the north coast and Top Speed Energy’s Skeena LNG at the Skeena Industrial Development Park just south of the Northwest Regional Airport, would help fill PNG’s line running west of Summit Lake near Prince George to Prince Rupert that began losing large-scale industrial customers over the years.

Without large volumes running through the line, PNG’s existing residential and commercial users have had to shoulder the cost of maintaining the line, resulting in natural gas user rates much higher than elsewhere in B.C.

PNG business development director Brock John confirmed the utility had signed contracts with Port Edward LNG and Top Speed sufficient for it to start detailed planning and regulatory approval applications leading to spending approximately $60 million between Terrace and Prince Rupert to enable it to pump more gas.

The project would involve service lines to the Port Edward LNG and Top Speed locations, upgrade four existing compressor stations and add two compressor stations, one at the industrial park and the other near Salvus between Terrace and Prince Rupert.

“Increasing the amount of natural gas flowing throughout the system, with new industrial loads for example, will have a positive impact on the delivery rates for our more than 20,400 customers in the region,” he said.

The natural gas line running from Summit Lake west to Prince Rupert is now at only about 20 per cent of capacity, John added.

Based on a timeline of anticipating regulatory approval from the B.C. Utilities Commission next summer, John said construction should start the fall of 2021 with completion the spring of 2024.

That timeline hinges on the progress of Port Edward LNG and Top Speed receiving their own regulatory approvals from the BC Oil and Gas Commission, arranging construction financing and signing up customers.

Port Edward LNG, a privately-held B.C. company, has purchased 37 acres in a private sale along Hwy 16 within the District of Port Edward and the council has given first and second readings to rezone the property for industrial use.

A first phase would produce 250,000 gallons a day with double that based on a second phase expansion.

First phase construction would work out to roughly one standardized container of super-cooled gas an hour that would be trucked to the Fairview Container Terminal for export to a number of Asian countries, explained Port Edward LNG president Chris Hilliard. He declined to identify those countries but did say it has customers lined up.

Hilliard also declined to provide the cost of the first phase development but did say it anticipates a construction start of early next year.

The gas would be cooled using electricity by connecting to a nearby BC Hydro substation.

Chinese-owned Top Speed Energy first unveiled its Skeena LNG plans in 2019, saying it wanted to build a small-scale facility processing 150,000 tonnes of liquefied natural gas a year at the Skeena Industrial Development Park. The plant would also supercool gas for storage in specialized containers.

The cooled product would then be transferred into specialized containers and stored on-site for short periods until it’s loaded onto trucks for delivery to domestic or international markets through the Fairview Container Terminal in Prince Rupert.

As with Port Edward LNG, the Skeena LNG location is close to PNG’s natural gas line and close to a B.C. Hydro line from which it would obtain power to run its facility.

The Skeena LNG project has been under review by the BC Oil and Gas Commission for much of 2020. Clark Roberts, CEO of Top Speed Energy, said he remains confident and hopeful that the project will be certified.

Once that certification is received, civil engineering for the Skeena LNG plant is set to begin in summer 2021, with construction expected to start in summer 2022 and a potential in-service date of early 2023.

Roberts confirmed that the Skeena LNG plant will be connected to the PNG line.

“We look forward to working with them and with the Terrace community,” Roberts said.

This year, Top Speed indicated it could also use power from Kitselas Geothermal Inc., a partnership of the Kitselas First Nation-owned Kitselas Development Corporation and Calgary-based Borealis GeoPower, should its own plans to tap hot water from geothermal springs near Lakelse Lake materialize.

Roberts said the Kitselas Geothermal project may not be ready in time to immediately service the Skeena LNG plant, but the plant will likely be constructed in a manner that would allow use of the geothermal energy once ready.

PNG began losing large-scale industrial customers beginning with the Skeena Cellulose pulp mill in 2001 followed by Methanex’s Kitimat methanol and ammonia facility in 2005 and West Fraser’s Kitimat pulp and paper mill in 2010.

That set the stage for increases from PNG’s remaining customers along its line so that this fall while a residential customer is paying a delivery charge of $12.470 per gigajoule of natural gas, a Fortis B.C. customer on the lower mainland is paying $5.615 a gigajoule. Natural gas utilities are not allowed to add to the cost of the gas itself.

John, the PNG representative, said it was still too early to estimate the kind of rate relief the utility’s existing customers could expect should Port Edward LNG and Top Speed go ahead.

“What we’re anticipating is rate stabilization for our customers,” he said.

PNG does expect, however, to recover its planned $60 million expenditure from what it will charge the two companies.

This is not the first time PNG has had hopes of filling its pipeline with new industrial customers.

It was involved in another small-scale LNG project at Prince Rupert called Triton LNG but shelved that in 2015.

The utility came close with another small-scale LNG project through its then-parent company, AltaGas of Calgary, in the early part of the last decade. It would have been a floating facility near Kitimat called Douglas Channel LNG.

But in 2016 with LNG prices on the decline and without waiting Asian customers, the project was cancelled.

John cautioned that its $60 million plan would only go ahead should Port Edward LNG and Top Speed both proceed.

The contracts it now has with the two companies, he said, have provisions to protect PNG and its customers from risk in case the projects do not move forward.

If only one project was to proceed PNG would likely scale back the need for all of the compressors and the location of the project would determine where and how much gas compression is required, he added.

This project is separate from another one PNG is planning, a $84.5 million expenditure to repair and replace sections of its existing pipeline along 80 kilometres from Salvus, between Terrace and Prince Rupert, and its Galloway pressure regulating station near the Galloway Rapids outside of Prince Rupert and Port Edward.

Its applied for regulatory approval through the B.C. Utilities Commission and is anticipating a two-year construction period beginning the middle of next year.

PNG is hosting two evening virtual information sessions, one on Nov. 25 and the other on Nov. 30. More details at www.png.ca/projects/recap.

(With files from Jake Wray)

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

The second of two massive hydro-electric turbines headed to the Site C Dam project near Fort St. John sits in Prince Rupert ready for the Jan. 27 trek across the province. The load is so large and heavy it needs counterweights on the 120 ft transport truck and trailer (Photo: K-J Millar/The Northern View)
Second of two giant turbines and multi-vehicle convoy hit the road to Site C Dam

Massive turbine load from Prince Rupert needs one truck pulling it and two trucks to push it

Hays Creek in Prince Rupert requires more than $1.5 million to repair the creek and walls built in the 1950s and 1960s, Prince Rupert City Council heard on Jan. 25. (Photo: K-J Millar/The Northern View)
Prince Rupert City Council briefs:

More than $1.5 million needed to restore Hays Creek in Prince Rupert

Staff at Acropolis Manor, a Prince Rupert long-term health care facility in April 2020 where no cases of COVID-19 were reported until an outbreak on Jan. 19, 2021. As of Jan. 25th, 32 people associated with the residence have tested positive for the virus. (Photo: K-J Millar/The Northern View)
Staff at Acropolis Manor a Prince Rupert long term health care facility, take pride in their work place that no COVID-19 cases have been reported in the facility during the pandemic.This photo taken, April 20, from outside, looking through a window shows staff adhering to strict protocols and best practices to keep residents happy and healthy. (Photo: K-J Millar/The Northern View)
COVID-19 numbers increase at Acropolis Manor – 32 infected

Prince Rupert man concerned about temp. staff from out of region working at long-term care facility

Ken Veldman vice president, public affairs and sustainability, at Prince Port Port Authority on Jan. 21 addressed local employers in an online presentation about a new community recruitment program to attract employees to Prince Rupert. (Photo: K-J Millar/The Northern View)
New recruitment campaign to be launched in Prince Rupert

Web platform will use community collaboration to attract new employees to Prince Rupert

People skate on a lake in a city park in Montreal, Sunday, January 10, 2021. THE CANADIAN PRESS/Graham Hughes
The end of hugs: How COVID-19 has changed daily life a year after Canada’s 1st case

Today marks the one year anniversary of COVID-19 landing in Canada

British Columbia Health Minister Adrian Dix looks on as Provincial Health Officer Dr. Bonnie Henry addresses the media during a news conference at the BC Centre of Disease Control in Vancouver B.C. (THE CANADIAN PRESS/Jonathan Hayward)
B.C. announces 485 new COVID-19 cases, fewest deaths in months

‘The actions we take may seem small, but will have a big impact to stop the virus,” urges Dr. Henry

Keith Thorpe/Peninsula Daily News
Search called off for small plane that went down in rough water south of Victoria

Plane bound for Port Angeles from Alaska believed to have one occupant, an Alaskan pilot

Royal B.C. Museum conservator Megan Doxsey-Whitfield kneels next to a carved stone pillar believed to have significance as a First Nations cultural marker by local Indigenous people. The pillar was discovered on the beach at Dallas Road last summer. Museum curatorial staff have been working with Songhees and Esquimalt Nation representatives to gain a clearer picture of its use. (Photo courtesy Royal BC Museum)
Stone carving found on Victoria beach confirmed Indigenous ritual pillar

Discussion underway with the Esquimalt and Songhees about suitable final home for the artifact

Former Vancouver Giants forward Evander Kane is seen here in Game 7 of the second round of the 2009 WHL playoffs against the Spokane Chiefs (Sam Chan under Wikipedia Commons licence)
Gambling debts revealed in details of bankruptcy filing by hockey star Evander Kane

Sharks left winger and former Vancouver Giants player owes close to $30 million total

Othman “Adam” Hamdan, pictured in front of Christina Lake’s Welcome Centre, was acquitted of terrorism related charges in 2017. He has been living in Christina Lake since November 2020. Photo: Laurie Tritschler
Man acquitted on terrorism charges awaits deportation trial while living in Kootenays

Othman Ayed Hamdan said he wants to lead a normal life while he works on his upcoming book

B.C. Premier John Horgan wears a protective face mask to help prevent the spread of COVID-19 prior to being sworn in by The Honourable Janet Austin, Lieutenant Governor of British Columbia during a virtual swearing in ceremony in Victoria, Thursday, November 26, 2020. THE CANADIAN PRESS/Jonathan Hayward
Premier Horgan calls jumping COVID vaccine queue ‘un-Canadian’

Horgan says most people in B.C. are doing their best to follow current public health guidelines

Prime Minister Justin Trudeau, left, and Vancouver Mayor Kennedy Stewart share a laugh while speaking to the media before sitting down for a meeting at City Hall, in Vancouver, on Friday August 30, 2019. (THE CANADIAN PRESS/Darryl Dyck)
Vancouver mayor, Health Canada to formally discuss drug decriminalization

Kennedy Stewart says he’s encouraged by the federal health minister’s commitment to work with the city

Downtown Fernie is pictured after a snowfall.

Most Read