Coastal GasLink is building 14 construction camps to house workers along the route of its pipeline. (Coastal GasLink photo)

First occupancy of CGL Houston camp expected for July 2020

Clearing the 78-kilometre pipeline section between Houston and Hazelton scheduled to start January

Occupancy of a workforce accommodation camp in the section of Coastal GasLink’s (CGL) pipeline route between Hazelton and Houston is slated to begin in July 2020.

A Nov. 18 update provided by the company said current construction on the project is focused on right-of-way clearing in Sections 1, 2, 3 and 8 of its route.

READ MORE: Unist’ot’en supporter arrested for denying contractor access to pipeline site

Fourteen per cent of the route has been cleared, the update stated.

“Rain and snow conditions are posing unfavourable conditions leading to clearing delays in some areas,” the report noted.

In Section 7, located between Hazelton and Houston, the development is focused on “environmental field studies for pre-construction.”

CGL also recently made inroads on a temporary-use permit (TUP) for the Huckleberry camp after the Regional District of Bulkley-Nechako (RDBN) reversed an earlier decision and approved TC Energy’s application for a TUP relating to the site.

The permit covers a 42.94 hectare area beside the Morice Owen Forest Service Road and is expected to house around 800 campers during its expected three to four years of operation.

At the Sept. 19 meeting during which the orginal applicaton was denied, some directors and resident Bobby Seinen expressed concerns over topics such as rough conditions on Morice River Rd., the volume of traffic and TC Energy’s (CGL parent company) communication with the public.

READ MORE: Wet’suwet’en hereditary chiefs demand stop work order against CGL

Pipe delivery for the Houston stockpile site is slated for December, while route clearing for Section 7 has been scheduled to start in January.

CGL is also currently working on grading and early site preparation work for the Huckleberry site, located some 30 kilometres south of Houston along the 78-kilometre stretch of pipeline route.

In the update the company said scheduled clearing has been going well despite the challenges provided by weather.

“Several milestones were recently achieved including the opening of the Sukunka Lodge site in Section 2,” the company said.

The site features a gym, lounge and 24-hour snack bar — as well as cell service and wi-fi — for its approximately 150 workers.

The development has not been without controversy, particularly within the Section 7 route.

The Unist’ot’en encampment and healing lodge had been blocking the company’s access to the site until hereditary chiefs agreed on Jan. 10 to abide by a B.C. Supreme Court interim injunction issued in December. The temporary injunction was originally scheduled to last until May 1, but the matter is still before the Court.

Earlier this month Police arrested a Unist’ot’en supporter after she attempted to prevent a Coastal GasLink (CGL) contractor from accessing the company’s worksite near Houston.

The woman said she was enforcing a protocol agreement requiring the company to give advance notice of any vehicles scheduled to pass through the Morice River Bridge checkpoint.

CGL subsequently acknowledged they had not followed the protocol.

“CGL were in contact with the RCMP and, after reviewing the incident, they advised that they had inadvertently not followed an agreement that they had made with the protestor regarding access,” stated an RCMP press release made the morning following the arrest.

“Given this information, the RCMP exercised discretion and released the protestor immediately with the understanding that the matter would be resolved between the parties.”



trevor.hewitt@interior-news.com

Like us on Facebook and follow us on Twitter

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Rio Tinto responds to U.S. aluminum import tariffs

The tariffs were imposed by President Donald Trump Aug. 6

Coastal GasLink breaks ground on meter station in Kitimat

Meter station marks final point on pipeline that stretches from Northeast B.C.

Oily rain runoff down the drain causes concern for Prince Rupert residents

Immediate action taken to alleviate any concerns, road paving contractor said.

B.C. fish harvesters receive long-awaited details on pandemic benefits

Applications to the $470-million federal assistance programs will open Aug. 24

Repaving coming for two sections of Nisga’a Hwy and Hubert St. in Gingolx

Drivers can expect some minor delays and single lane alternating traffic

53 new COVID-19 cases, no new deaths cap off week of high infection rates in B.C.

Roughly 1,500 people are self-isolating because they either have COVID-19 or have been exposed to it

VIDEO: U.S. Air Force pilot does fly-by for B.C. son amid COVID border separation

Sky-high father-son visit plays out over White Rock Pier

3 Vancouver police officers test positive for COVID after responding to large party

Union president says other officers are self-isolating due to possible exposure

New mothers with COVID-19 should still breastfeed: Canada’s top doctor

Dr. Theresa Tam made the recommendation during World Breastfeeding Awareness Week

Collapse of Nunavut ice shelf ‘like losing a good friend:’ glaciologist

The ice shelf on the northwestern edge of Ellesmere Island has shrunk 43 per cent

B.C. wildfire crews have battled 111 blazes in the last seven days

Twenty-nine fires remain active, as of Friday (Aug 7)

‘We don’t make the rules’: Okanagan pub owner says staff harassed over pandemic precautions

‘If you have six people plus a baby, guess what? That’s seven’ - West Kelowna Kelly O’Bryan’s owner

T-Rex earns big bids at B.C. dino auction

Over 500 dino-themed lots sold to buyers from across North America

Remembering Brent Carver: A legend of Broadway who kept his B.C. roots strong

Over the years, the Cranbrook thespian earned his place as one of Canada’s greatest actors

Most Read