B.C. to go ahead with Site C dam, with new $16B budget and delayed to 2025

Reviews recommend more oversight, beefed up foundation stability work

Premier John Horgan says his government will continue building the Site C mega dam in northeastern B.C., with an increased budget of $16 billion and a one year delay.

Last August, the government commissioned a special review after BC Hydro acknowledged a serious concern about the dam’s foundational stability. Those reports were made public Friday (Feb. 26), with the province accepting all recommendations.

Special advisor Peter Milburn recommended additional oversight, but did not find evidence of mismanagement.

The government calculated it would cost $10 billion to terminate the dam, and that it will be preferable to complete Site C at the higher price than to absorb the loss. Horgan said cancelling the dam would have an immediate impact to ratepayers of an estimated 26 per cent rate increase over 10 years.

About $6 billion has already been spent, and construction on the dam is over half complete, BC Hydro said.

The Peace River has been diverted, the coffer dams are done and two of the massive turbines have arrived from Brazil. Energy Minister Bruce Ralston also said most of the environmental impacts have already occurred.

In reaction to the announcement, Green Party leader Sonia Furstenau criticized the decision, saying “this isn’t the last time [British Columbians] are going to hear about costs going up.” The Green Party have consistently opposed the dam.

The BC Liberals, who initially approved the dam under former premier Gordon Campbell, have not released an official statement. Interim leader Shirley Bond did re-tweet a comment from pundit Shane Mills saying the NDP “have completely bungled oversight of project of project that was on-time and on-budget.”

RELATED: BC Liberal critic blasts ‘lack of transparency’ on Site C

When the Liberals left power it 2017, they said the project was on time and on budget, but when the BC Utilities Commission reviewed the project later that year, they called that claim into question, predicting probable cost overruns and delays.

The Union of B.C. Indian Chiefs has also consistently opposed the dam on the grounds that the First Nations in the area were not adequately consulted and did not give their consent – impact benefit agreements notwithstanding – despite the province’s voice interest in reconciliation.

Kukpi7 Judy Wilson, UBCIC Secretary-Treasurer, added that the UN Committee on the Elimination of Racial Discrimination has called on Canada to suspend Site C until it has the free, prior and informed consent of Indigenous Peoples.

RELATED: Open letter urges B.C. to pause work at Site C dam to review costs, geotechnical issues

As for geotechnical concerns, engineers virtually evaluated the small movement shifts that had been observed and recommended solutions to shore up the strength of the foundation. These necessary changes plus COVID-19 adjustments make up about half of the increases costs, while the remaining $2.6 billion is set for other unrelated cost overruns.

The actual rate increase from completing the project are unknown, as they will not take effect until the dam is complete – now estimated for 2025. BC Hydro has estimated a roughly $36 annual increase for an average rate payer.

RELATED: First Nation calls for release of Site C report in open letter to premier

The dam has been controversial since the 1980s when it was first proposed as a series of dams on the Peace River. Supporters say the mega dam will supply B.C. with stable energy to meet growing capacity needs.

Those opposed group under a variety of reasons, a primary critique being the ballooning budget.

Site C was originally approved with an $8.8 billion budget in 2014. It increased to $10.7 billion after the BC Utilities Commission reviewed the project in 2017 when the NDP took over government.

Concerns around dam stability have been raised by the public for years. Other complaints are about the ecological impact, First Nations rights in the area, and whether B.C. really needs the power supply.

Do you have something to add to this story or something else we should report on? Email: zoe.ducklow@blackpress.ca


BCHydroenergy sector

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Dreamfish are hung on the fence at Annunication School in Prince Rupert on April 17 as part of the Stream of Dream eco-education program teaching about local watersheds and salmon habitats. (Photo: K-J Millar/The Northern View)
Stream of Dreams fish swim the fence at Prince Rupert School

Students at Annunciation school learned about watershed protection and salmon habitat

B.C. Finance Minister Selina Robinson outlines the province’s three-year budget in Victoria, April 20, 2021. (B.C. government video)
B.C. deficit to grow by $19 billion for COVID-19 recovery spending

Pandemic-year deficit $5 billion lower than forecast

Registered Nurse, Teresa Friesen immunizes Dunrovin resident, Richard Brophy. Resident’s at the home were the first in Quesnel to receive COVID-19 vaccines. (Submitted Photo)
COLUMN: Vaccine floodgates should be opened

This editor’s column first appeared in the April 14 edition of the Quesnel Cariboo Observer

BC CDC mapping for the week ending April 4, shows a sharp decrease in COVID-19 cases to 27 in Prince Rupert down 45 from the week prior. (Image: BCCDC)
Sharp decline in Prince Rupert COVID-19 cases

Prince Rupert lab-confirmed cases are down 62.5 per cent in one week

A large crowd protested against COVID-19 measures at Sunset Beach in Vancouver on Tuesday, April 20, 2021. (Snapchat)
VIDEO: Large, police-patrolled crowds gather at Vancouver beach for COVID protests

Vancouver police said they patrolled the area and monitored all gatherings

A teacher-librarian in Nanaimo was fired in 2019 for checking out an age-inappropriate graphic novel to a student. The discipline agreement was published Wednesday, April 21. (News Bulletin file photo)
B.C. teacher-librarian fired for checking out too-graphic graphic novel to student

Teacher had been previously disciplined and suspended on two occasions

Former University of Victoria rowing coach Barney Williams is photographed in the stands during the Greater Victoria Invitational at CARSA Performance Gym at the University of Victoria in Victoria, B.C., on Friday, November 29, 2019. THE CANADIAN PRESS/Chad Hipolito
Former B.C. university rowing coach ‘deeply sorry’ after complaints

Barney Williams says he’s been committed to ensuring no other member of the roster had a similar experience

Aria Pendak Jefferson cuddles ChiChi, the family cat that ran away two years ago in Ucluelet. The feline was missing until Courtney Johnson and Barry Edge discovered her in the parking lot of the Canadian Princess earlier this month. Aria and her parents were reunited with ChiChi in a parking lot in Port Alberni. (SUSAN QUINN/ Alberni Valley News)
B.C. girl’s wish granted as her cat came back, two years later

Courtenay family reunited with cat that went missing in Ucluelet in 2019

(Bandstra Transportation photo)
Smithers family-owned business institution sold to publicly-traded company

Bandstra Transportation and Babine Trucking acquired by Mullen Group

FILE – The Instagram app is shown on an iPhone in Toronto on Monday, March 19, 2018. THE CANADIAN PRESS/Graeme Roy
Judge acquits B.C. teen boy ‘set up’ on sex assault charge based on Instagram messages

The girl and her friends did not have ‘good intentions’ towards the accused, judge says

Kai Palkeinen recently helped a car stuck on the riverbed near the Big Eddy Bridge. While the car could not be saved, some of the driver’s belongings were. It’s common for vehicles to get stuck in the area due to significantly changing river levels from Revelstoke Dam. (Photo by Kai Palkeinen)
“I just sank a car’: Revelstoke resident wants Columbia River better protected

Although it’s not permitted, the riverbed near the city is popular for off roading

Meng Wanzhou, chief financial officer of Huawei, walks down the street with an acquaintance after leaving B.C. Supreme Court during a lunch break at her extradition hearing, in Vancouver, B.C., Thursday, April 1, 2021. A judge is scheduled to release her decision today on a request to delay the final leg of hearings in Meng Wanzhou’s extradition case. THE CANADIAN PRESS/Rich Lam
B.C. judge grants Meng Wanzhou’s request to delay extradition hearings

Lawyers for Canada’s attorney general had argued there is no justification to delay proceedings in the case

Most Read