Installation of a fifth and sixth generating unit at Mica dam has taken eight years.

Dam expansion done as BC Hydro demand slumps

Four per cent rate increase expected next year to keep up with big maintenance, construction of Site C on the Peace River

BC Hydro has completed one of its mega-projects, expansion of the Mica Dam on the Columbia River to full capacity, as the utility weathers a slump in mining and continued delays in liquefied natural gas projects.

The addition of two water turbines to Mica cost $714 million, plus a new high-voltage transmission line to carry power to the Lower Mainland and Vancouver Island. BC Hydro has also moved up plans to add a sixth turbine at the Revelstoke Dam, as work continues on the Site C project on the Peace River.

[A look inside the Mica Dam project here]

With major upgrades at the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island also underway, BC Hydro has applied for a four per cent rate increase to take effect on April 1, 2017. That follows increases of nine and six per cent in the past two years, mainly to finance major projects and pay down debt.

The four per cent rate is a one-year interim application to the B.C. Utilities Commission, which would add about $4 a month to the average residential electricity bill. Faced with mine shutdowns and uncertainty in large LNG projects, BC Hydro put off its three-year rate proposal when it filed the application in February.

Under a 10-year rate plan imposed by the B.C. government, rates are to increase 3.5 per cent in 2018 and three per cent in 2019. After that, authority over rate setting is to return to the BCUC.

Despite the current downturn for industrial customers, BC Hydro projects demand to increase 40 per cent over the next 20 years, due to population and industrial growth.

It has also scheduled major maintenance at Mica, with two original turbines built in the 1970s due to come out of service for 18 months each.

The B.C. government has proposed to Ottawa that a second power grid link to Alberta be built to help that province retire its coal-fired power plants.

 

Just Posted

Council briefs: Gurney marks one year as Lester Centre’s manager, marina revenues down

Council supports Métis Awareness week but has concern over raising Infinity Flag

In-brief: Electric charging station available in Prince Rupert, Metlakatla senior housing taking applications

Weather dampens paving plans on McBride, The Northern View Cannery Road Race is coming down the road

Prince Rupert shuttle service set to get underway

New shuttle bus between Prince Rupert and Terrace

VIDEO: Kaien Anti-Poverty Society hoping to raise $20K in 50/50 community bingo nights

KAPS is looking to raise money for a new vehicle to support their growing food program

Heart of Our City: Kaps off to Colleen Hermanson

Colleen Hermanson began working in social services as early as 1968

Captain, all-star, MVP, and all about the team

Brittanne O’Connor’s drive to create Prince Rupert’s own women’s team has led to success and inspiration

The Northern View announces inaugural Tyee Fishing Derby in Prince Rupert

More than $7,000 up for grabs for biggest legal salmon and halibut

The Northern View 2019 Readers Choice

It’s that time of year again! Vote online or at the Prince Rupert office before noon on Aug. 30

B.C. manhunt suspects left cellphone video before they died: family

Family member says Kam McLeod, Bryer Schmegelsky recorded final wishes

Okanagan bus driver assaulted for asking patron not to smoke

59-year-old in hospital with non-life threatening injuries

B.C. sets rules for ride hailing, same minimum fee as taxis

Larger operating areas seen as threat by cab companies

Two hiking families team up to extinguish fire in B.C. backcountry

Children and their parents worked for three hours to ensure safety of the popular hiking region

Most Read